CLIENT
Province of Cuneo – Alba and Mondovì Road Infrastructure Department

CONTRACTOR
Edilsystem S.r.l.

CONTRACT SCOPE
Structural strengthening works on the beams of the S. Stefano Belbo viaduct at km 13+400 – Provincial Road S.P. 592 (Lot 1)

PROJECT LOCATION
Santo Stefano Belbo (CN) – S.P. 592

WORKS PERIOD
2017 – 2018

Description of the Works

Structural restoration and regulatory upgrading of the viaduct’s prestressed reinforced concrete beams.

The project addressed severe deterioration of the lower beam flanges and oxidation of the prestressing tendons caused by the infiltration of rainwater and de-icing salts from the bridge deck.

The works carried out included:

  • Removal of deteriorated concrete and application of passivating anti-corrosion treatments to the exposed reinforcement and steel wires.
  • Restoration of the concrete cover through the application of special non-shrink repair mortars.
  • Structural strengthening (FRP):
  • Composite system configuration:

The application of the composite strengthening system increased the ultimate bending resistance of the beams, compensating for the loss of efficiency of the deteriorated prestressing tendons without increasing the self-weight of the structure.